A lessons learned brought to our attention by Suffolk-Roel Superintendent Chris Monahan was ACT compression posts interfering with MEP systems during field installation. For Middle School #3 all ACT and pendant light compression posts were added to the BIM model and coordinated before construction.
ACT compression post:
Pendant light compression post:
Compression post clashes identified in BIM model:
Compression post and MEP clashes resloved in coordinated BIM model:
Compression post installed per coordinated location in BIM model: