Even the small buildings benefit from BIM

Can you identify the 4 issues in this corner of the 4,500 sq.ft. library at Little Mountain?:

and the answer is...

1.  Exposed fire protection pipe.
2.  Light fixture in the path of the projector image.
3.  Light fixture in sloped soffit.
4.  Wall diffuser in soffit.
Labels: MEP coordination, Project - Little Mountain, Software - Navisworks
Older Post Home

Labels

  • 4D
  • 5D
  • 6D
  • BIM in the field
  • Lessons Learned
  • MEP coordination
  • Project - Bell Education Center
  • Project - COC
  • Project - Colton High School
  • Project - Colton Middle School
  • Project - Icon
  • Project - LATTC
  • Project - LAUSD 9th St.
  • Project - LAUSD HS #12
  • Project - LAUSD MS #3
  • Project - Little Mountain
  • R and D
  • Return on Investment
  • Seminar/Conference
  • Software - CAM 2011
  • Software - DProfiler
  • Software - Ecodoums
  • Software - Navisworks
  • Software - on-trac
  • Software - Sketchup
  • Software - Solibri
  • Tips and Tricks
  • Training
  • Virtual Mock-up
  • West Coast BIM Team

Total Pageviews

Simple theme. Powered by Blogger.